The Goldsmith Metropolitan District (the “District”) will be constructing a new well and irrigation water infrastructure near the intersection of Ulster Street and Belleview Avenue. This project is necessary to maintain a reliable supply of irrigation water for the Denver Tech Center (DTC). The map above shows the location of the new well (red pin), and the blue circle reflects a boundary of 700 feet from the well location.
Construction of the well will require 24-hour drilling operations for approximately 3 weeks. In order to minimize noise impacts from this project, the District will be installing temporary sound walls around the drilling site. The District has conducted sound studies and designed these sound walls to reduce the noise levels below 75 decibels, as required by the noise variance requirements of the Denver Department of Public Health & Environment.
The approximate schedule of project activities is as follows:
Installation of Sound Walls January 4 - January 7, 2023
Equipment Mobilization/Daytime Construction Activities January 5 - January 9, 2023
24-hour Drilling Operations January 9 - February 1, 2023
Final Well Completion/Testing (some nighttime activities) February 6 - February 24, 2023
We appreciate your patience and understanding as the District works to maintain and enhance the infrastructure within the Denver Tech Center. For questions or concerns, please contact the Goldsmith Metropolitan District at 303-773-1700 or at admin@goldsmithmetro.org.
Please continue to visit this page for the most up-to-date information related to this project.
Para obtener información en español, envíe un correo electrónico a admin@goldsmithmetro.org
Copyright © 2023 Goldsmith Metropolitan District - All Rights Reserved.