The Goldsmith Metropolitan District (the “District”) will be constructing a new well and irrigation water infrastructure near the intersection of Ulster Street and Belleview Avenue. This project is necessary to maintain a reliable supply of irrigation water for the Denver Tech Center (DTC). The map above shows the location of the new well (red pin), and the blue circle reflects a boundary of 700 feet from the well location.
The 24-hour drilling operations for the well have been completed. Construction activities around the well site will continue for the remainder of 2023, however nighttime construction will be complete in February.
The schedule for upcoming activities are as follows:
Final Well Completion/Testing February 6 - February 24, 2023
Pump Test (24/7 work) February 20 - February 23, 2023
Removal of Sound Walls March 6 - March 10, 2023
Design/Construction of Control Vault March - December 2023
We appreciate your patience and understanding as the District works to maintain and enhance the infrastructure within the Denver Tech Center. For questions or concerns, please contact the Goldsmith Metropolitan District at 303-773-1700 or at admin@goldsmithmetro.org.
Please continue to visit this page for the most up-to-date information related to this project.